Parish East:
Terrazzo installs tracking for 8/21. 21st Street is again open to traffic, but Guadalupe will be restricted shortly, the existing covered walkway will go away and a new covered walkway will be installed. All TCO-required sidewalks are done. The remaining alley concrete is likely to be poured by the end of the week. Courtyard landscaping crews are digging tree wells. All berms have been constructed.